Latest figures

FY2026 revenue fell 10.5% y/y to SGD101.573mn while gross profit rose to SGD36.042mn; cash was SGD33.605mn and debt including leases was SGD1.584mn at June 2026, while contracted work still to be performed was SGD111.183mn.

Business model

Lum Chang Creations restores conservation buildings, fits out interiors and undertakes additions and alterations.

Main risk

The central risk is that project mix and completion-cost revisions make recent margins difficult to repeat and billing lags work performed.

Next proof

The next test is 1HFY2027 results, expected in February 2027, for project margins, cash collection and replacement contracts.

Latest reported figures

FY2026 revenue was SGD101.573mn and gross profit SGD36.042mn. Remaining performance obligations were SGD111.183mn at 30 June 2026.

Earlier discussion below is dated historical analysis.

Also on file: historical private research.

Business strengths and risks

The live questionCan the dividend be sustained after the payout intention ends, particularly if project margins return towards historical levels?The latest dividend exceeded free cash flow after leases as stronger reported margins coincided with weaker cash conversion.

What improved

Higher-margin projects progressed and lower net warranty expense supported profit, showing that project selection and delivery can lift earnings even as activity declines.

What became more demanding

Contract assets increased as work ran ahead of billing, and customer advances were consumed; collections now need to catch up with the stronger reported margin.

Strongest alternative explanation

Billing and collection can lag project recognition, so weaker cash conversion can reflect the timing of progress claims rather than an eventual loss on the work.

The decisive missing fact

Future project margins, cash collection and the board's dividend decisions will show whether cash generation can support the full distribution.

Private library

On this page

Specialist work, fixed-price commitments

Execution is the business. Lum Chang Creations (SGX: LCC) restores heritage buildings, fits out interiors and undertakes addition and alteration works under fixed-price contracts. Government, institutional and commercial customers commission projects across infrastructure, hospitality, retail and other properties. LCC coordinates procurement and subcontractors, then bills certified progress. Revenue follows costs incurred relative to estimated total contract costs.

The parent remains influential. After the reorganisation from Lum Chang Holdings, LCC listed on Catalist on 21 July 2025 and transferred to the Mainboard on 16 July 2026. Lum Chang Holdings retained 64.15% at 11 September 2026. LCC continues to use parent-group services, premises and branding.

FY2026 related-company sales were SGD3.201m and other related-party sales SGD0.034m. The parent management fee was SGD0.297m; parent project-management fees were SGD0.216m.

Business anatomy · from inputs to customer value

LCC manages the contract while specialists execute the work

Clients commission restoration, conservation, fit-out or alteration projects; LCC prices and supervises them while subcontractors perform most physical construction.

Follow the operating chain from demand or inputs to customer outcome and cash.

  1. Customer needClient brief

    Commission the site work

    What happensA government, institutional or commercial client defines a restoration, fit-out or alteration job.

    Commercial triggerThe tender or negotiated contract sets the scope and price.

  2. Company actionMain contractor

    Price and programme it

    What happensLum Chang Creations plans the sequence, procures packages and supervises the overall contract.

    Value createdIts value is project control, coordination and contractual delivery.

  3. Delivery partnerSpecialists

    Perform the physical works

    What happensSpecialist subcontractors restore, alter or fit out the site under LCC’s management.

    Cost structureSubcontractor and material costs absorb most project spend.

  4. Cash triggerCustomer acceptance

    Certify and collect

    What happensThe completed stage is inspected, certified and billed to the client.

    Cash triggerThe client pays for certified work. Contract margin reflects recognised revenue less recognised project costs.

AI-assisted illustration, representative only. Figures from company filings to 24 Nov 2026.

Cash and balance-sheet risks

Value lever
Project margin and working-capital turnover on restoration, alteration and fit-out contracts.
Cash bottleneck
Subcontractors and materials are paid before completed work is certified and retention is released.
Balance-sheet pressure
Execution is constrained if operating cash and bonding lines cannot cover payroll, completion costs and project guarantees.
Next proof
Collection following the stronger margin, certified progress, retention receipts and warranty costs.
Text version of this comic
  • Customer need · Commission the site work A government, institutional or commercial client defines a restoration, fit-out or alteration job. Commercial trigger: The tender or negotiated contract sets the scope and price.
  • Company action · Price and programme it Lum Chang Creations plans the sequence, procures packages and supervises the overall contract. Value created: Its value is project control, coordination and contractual delivery.
  • Delivery partner · Perform the physical works Specialist subcontractors restore, alter or fit out the site under LCC’s management. Cost structure: Subcontractor and material costs absorb most project spend.
  • Cash trigger · Certify and collect The completed stage is inspected, certified and billed to the client. Cash trigger: The client pays for certified work. Contract margin reflects recognised revenue less recognised project costs.

Profit strengthened; cash lagged

Revenue by half; second halves are annual revenue less the first half
Chart notes.

Higher-margin work lifted earnings. FY2026 revenue fell 10.5% y/y to SGD101.6mn as project timing and progress reduced recognition. Gross profit rose SGD13.7mn y/y to SGD36.0mn, lifting attributable profit 72.4% y/y to SGD22.3mn despite a SGD2.3mn rise in administrative expenses and SGD2.2mn higher tax. Gross margin rose y/y to 35.5% from 19.7% as higher-margin projects progressed. We think the margin mix matters more than the revenue decline, but project-level contributions are not disclosed.

Singapore remains the core market. Singapore revenue fell 11.0% y/y to SGD100.9mn in FY2026, while Malaysia rose 233.7% y/y to SGD0.7mn. Lum Chang Creations reports one operating segment and does not disclose profit by business line. Its SGD141.7mn order book at 25 August 2026 includes the SGD32.9mn Teck Ghee Station contract secured in July 2026. We think the order book supports activity, but its future margin is unconfirmed.

Annual results · SGD million unless stated; June year end
PeriodRevenueGross profitGross margin %PBTPATMIOperating cash flowNet cash, derived
FY202214.0361.80212.80.5930.503-1.4771.186
FY202339.4308.25820.95.7124.5362.2053.154
FY202458.97310.65218.16.7834.7239.51510.689
FY2025113.55022.38119.716.50412.91122.60625.764
FY2026101.57336.04235.528.08422.26213.18432.021

Earlier growth came from project progress. The offer document links the earlier expansion to more active projects and higher construction activity. The following annual report attributes the next revenue increase to progress on existing work and new projects. Timing and mix then lowered revenue in the latest year.

Half-year results · SGD million unless stated; second-half flows derived
PeriodRevenueGross profitGross margin %PBTPATMIOperating cash flowNet cash, derived
1HFY202435.1996.87419.54.9553.2865.062Not recovered
2HFY202423.7743.77815.91.8281.4374.45310.689
1HFY202540.8368.61121.16.7045.3794.6599.721
2HFY202572.71413.77018.99.8007.53217.94725.764
1HFY202653.51517.90233.513.81910.96618.78944.074
2HFY202648.05818.14037.714.26511.296-5.60532.021

Procurement helped the first-half margin. The interim filing attributes stronger earnings to higher-margin work and procurement efficiencies. The latest second half sustained that margin strength while cash moved in the opposite direction.

PBT means profit before tax; PATMI means profit attributable to owners. Net cash is cash and equivalents less all borrowings, including leases and hire purchase. Half-year net cash is a closing balance, not an annual-minus-interim flow.

What the numbers say

Second-half sales eased sequentially. Revenue fell 10.2% h/h to SGD48.1mn in 2HFY2026, while gross margin rose h/h to 37.7% from 33.5%. The company does not quantify the project drivers of the sequential change.

Derived: [revenue|FY2026] - [revenue|1HFY2026]. AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3.Derived: ([revenue|2HFY2026] / [revenue|1HFY2026] - 1) * 100. AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; HY2026 PDF 3; printed 3.Derived: [gross_profit|2HFY2026] / [revenue|2HFY2026] * 100. AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3.Derived: [operating_cash_flow|FY2026] - [operating_cash_flow|1HFY2026]. AR2026 PDF 71; printed 69; HY2026 PDF 7; printed 7.

Lower warranty expense helped earnings. Net warranty expense fell from SGD3.404m to SGD0.658m. The SGD2.746m reduction equals 23.7% of the PBT increase: charges fell SGD1.250m and releases rose SGD1.496m. This explains part of the improvement; the filings give no full project-mix and estimate-change bridge.

Derived: [warranty_charge|FY2026] - [warranty_release|FY2026]. AR2026 PDF 98; printed 96.Derived: [net_warranty_expense|FY2025] - [net_warranty_expense|FY2026]. AR2026 PDF 98; printed 96.Derived: [warranty_expense_reduction|FY2026] / [profit_before_tax_change_yoy|FY2026] * 100. AR2026 PDF 98; printed 96; AR2026 PDF 66; printed 64.

Cash conversion weakened. Operating cash flow divided by PATMI was 59.2% in FY2026 versus 175.1% in FY2025. Contract assets rose as work ran ahead of billing, while customer advances were consumed. The payables and provisions movement also absorbed cash.

Derived: [operating_cash_flow|FY2026] / [patmi|FY2026] * 100. AR2026 PDF 71; printed 69; AR2026 PDF 66; printed 64.Derived: [operating_cash_flow|FY2025] / [patmi|FY2025] * 100. AR2026 PDF 71; printed 69; AR2026 PDF 66; printed 64.

Working capital absorbed more funding. Broad working capital reached SGD23.181m, or 22.8% of revenue, from negative SGD0.440m at June 2025. Excluding the SGD9.857m placement receivable leaves SGD13.324m, or 13.1%. This separates financing settlement from customer collection.

Derived: [contract_assets|FY2026] + [trade_other_receivables_current|FY2026] + [trade_other_receivables_noncurrent|FY2026] - [trade_other_payables_current|FY2026] - [trade_other_payables_noncurrent|FY2026] - [contract_liabilities|FY2026]. AR2026 PDF 68; printed 66.Derived: [working_capital_ex_placement|FY2026] / [revenue|FY2026] * 100. AR2026 PDF 68; printed 66; AR2026 PDF 93,100; printed 91,98; AR2026 PDF 66; printed 64.

Replenishment exceeded first-half revenue. The headline book rose from SGD112.8m at June 2025 to SGD132.0m at December 2025. Closing book less opening book plus recognised revenue implies approximately SGD72.7m of net additions, a derived book-to-bill of 1.36 times. Variations, cancellations and scope changes can affect that residual; it is not gross contract wins.

Derived: [order_book|1HFY2026] - [order_book|FY2025] + [revenue|1HFY2026]. HY2026 PDF 23; printed 23; AR2025 PDF 8-9; printed 6-7; HY2026 PDF 3; printed 3.Derived: [implied_new_contracts|1HFY2026] / [revenue|1HFY2026]. HY2026 PDF 23; printed 23; AR2025 PDF 8-9; printed 6-7; HY2026 PDF 3; printed 3; HY2026 PDF 3; printed 3.

Cash provides flexibility. At 30 June 2026, net cash including leases rose to SGD32.021mn from SGD25.764mn y/y: operations SGD13.184mn and share proceeds SGD9.585mn, less SGD14.805mn dividends and SGD2.026mn capex; other movements SGD0.319mn. Gross gearing fell y/y to 3.1% from 5.5% as equity rose to SGD50.490mn from SGD23.241mn and borrowings rose to SGD1.584mn from SGD1.281mn. EBIT interest cover was 184.6x in FY2026 versus 285.6x in FY2025; free cash flow after leases covered dividends 0.75x in FY2026 versus 1.70x in FY2025. We think liquidity remains comfortable despite dividend shortfall.

Net-cash bridge · SGD million; signed contributions
DriverAmount
Operating cash flow13.184
Share-issue cash receipts9.585
Equipment purchases-2.026
Equipment disposal receipts0.975
Interest received0.477
Dividends to owners-14.805
Subsidiary minority dividends-0.245
Lease and hire-purchase payments-0.679
Subsidiary disposal receipts0.030
Exchange movement0.064
Increase in borrowings deducted-0.303
Derived: [cash_bridge_operating|FY2026] + [cash_bridge_capex|FY2026] + [cash_bridge_disposals|FY2026] + [cash_bridge_interest|FY2026] + [cash_bridge_dividends|FY2026] + [cash_bridge_nci_dividends|FY2026] + [cash_bridge_equity_proceeds|FY2026] + [cash_bridge_leases_hire|FY2026] + [cash_bridge_subsidiary_sale|FY2026] + [cash_bridge_fx|FY2026] + [cash_bridge_debt_change|FY2026]. AR2026 PDF 71; printed 69; AR2026 PDF 71,110; printed 69,108; AR2026 PDF 68; printed 66.

The book is concentrated; the definitions differ

A few projects carry much of delivery. The SGD141.7m outstanding book at 25 August 2026 was reconfirmed on 16 October 2026. The five largest projects accounted for more than 70%. Original award values are not remaining revenue, so adding named awards cannot establish the remaining-book concentration.

Audited unsatisfied performance obligations at each June year end · SGD million
PeriodTotalRelated companies
FY202255.95814.270
FY202349.78514.005
FY2024150.95911.945
FY2025112.7753.703
FY2026111.1830.502

These audited unsatisfied performance obligations exclude short-duration and time-billed contracts and constrained variable consideration. They are not the full headline order book. At the latest June year end, the related-company share was a derived 0.45% (0.502 / 111.183 × 100). The related-company column shows the disclosed relationship component of these obligations; no current related-company share of the August headline book is established.

Headline order-book observations · SGD million
DateBookSource
December 2024142.6OFFER, PDF 115
June 2025112.8AR2025, PDF 8–9
December 2025132.0HY2026, PDF 23
25 August 2026; reconfirmed 16 October 2026141.7SH-QA, PDF 1

Dated developments

  • 16 July 2026: trading transferred from Catalist to the Mainboard.
  • 20 October 2026: LCC answered the SGX query and corrected the managing director’s performance-bonus calculation.
  • 22 October 2026: shareholders approved the final dividend.
  • 10 November 2026: the replacement notice corrected the managing director’s acquisition quantity.

Corrections matter alongside execution

The bonus calculation required correction. SGX queried the annual report on 15 October 2026. In its 20 October response, LCC distinguished the performance bonus from the annual wage supplement and corrected the calculation for minority interests and exceptional items. The managing director’s performance bonus fell by SGD30.11 thousand (SGD30,110).

The replacement notice governs the purchase. The 10 November 2026 replacement filing records managing director Lim Thiam Hooi’s 6 November acquisition of 124,300 shares and a resulting interest of 10.41%. It supersedes the original quantity of 114,400 shares.

Dividend approved; settlement unconfirmed

The AGM approved the FY2026 final dividend of 1.0 cent per share on 22 October 2026. The dividend notice scheduled payment for 13 November 2026. No recovered filing confirms settlement.

Cash collection is the next test

Watch cash alongside margin. At 1HFY2027 results, expected by mid-February 2027, compare operating cash flow, contract assets, advances and warranty provisions with project margins. The exact results date is unannounced in the supplied filing record. New awards and collection on existing work will show whether the stronger margin can support continued activity.

What we watch. What project mix and margins will be realised as the order book is delivered? Which projects explain the sequential revenue decline and margin improvement? How will working capital and project cash collections affect future dividend cover?

What you can watch yourself

Every other test on this page waits for the company to file. These do not. Each row is a series you can look up yourself, free, today — with the level this reading was built against, the levels that would put it in question, and what the series cannot tell you.

BCA total construction demand, S$ billion of contracts awarded

BCA's January construction-prospects release; read total construction demand, and the August review that revises it. Building and Construction Authority, Singapore

Last recorded
50 S$bn, 2026-01-22
What the reading assumes
50.5 S$bn (BCA reported actual, 2025)
Watch / alert
47 and 39 S$bn, on a move below — currently between the assumed level and the watch level
How often to look
twice yearly, at the January forecast and the August review (the series prints event)

What it points to. Fit-out work is let late in a project, so the award series is the pipeline the order book is drawn from, with a longer lag than for structural trades.

Direction only — this pack does not carry a coefficient from this series to reported earnings.

What it cannot tell you. Construction demand is the nominal value of contracts AWARDED, not work done: the company's page already records that BCA publishes no lag interval between award and output, so this series cannot time revenue. It is also a national aggregate, and a single large public award can move it without touching this company's addressable work.

Settled by the next full-year results and order-book disclosure, due 2027-09-30. Lead time: award to output runs into following years; BCA states the lag but does not quantify it.

Notes and sources

Share prices use saved Yahoo Finance market data for LCC.SI, including the 20 November 2026 close; the saved response was not independently refreshed for this page.

Net cash deducts all borrowings including leases; gross gearing is all borrowings including leases divided by total equity. EBIT is profit before tax plus finance expense. Free cash flow after leases is operating cash flow less equipment purchases and lease principal and interest; dividend cover uses dividends in respect of each financial year.

Table sources and arithmetic

FY2022: revenue: OFFER PDF 198; printed A-6; gross_profit: OFFER PDF 198; printed A-6; gross_margin: derived [gross_profit|FY2022] / [revenue|FY2022] * 100; OFFER PDF 198; printed A-6; profit_before_tax: OFFER PDF 198; printed A-6; patmi: OFFER PDF 198; printed A-6; operating_cash_flow: OFFER PDF 201-202; printed A-9 to A-10; net_cash: derived [cash_and_equivalents|FY2022] - [borrowings|FY2022]; OFFER PDF 199; printed A-7.

FY2023: revenue: OFFER PDF 198; printed A-6; gross_profit: OFFER PDF 198; printed A-6; gross_margin: derived [gross_profit|FY2023] / [revenue|FY2023] * 100; OFFER PDF 198; printed A-6; profit_before_tax: OFFER PDF 198; printed A-6; patmi: OFFER PDF 198; printed A-6; operating_cash_flow: OFFER PDF 201-202; printed A-9 to A-10; net_cash: derived [cash_and_equivalents|FY2023] - [borrowings|FY2023]; OFFER PDF 199; printed A-7.

FY2024: revenue: AR2025 PDF 68; printed 66; gross_profit: AR2025 PDF 68; printed 66; gross_margin: derived [gross_profit|FY2024] / [revenue|FY2024] * 100; AR2025 PDF 68; printed 66; profit_before_tax: AR2025 PDF 68; printed 66; patmi: AR2025 PDF 68; printed 66; operating_cash_flow: AR2025 PDF 73; printed 71; net_cash: derived [cash_and_equivalents|FY2024] - [borrowings|FY2024]; AR2025 PDF 70; printed 68.

FY2025: revenue: AR2026 PDF 66; printed 64; gross_profit: AR2026 PDF 66; printed 64; gross_margin: derived [gross_profit|FY2025] / [revenue|FY2025] * 100; AR2026 PDF 66; printed 64; profit_before_tax: AR2026 PDF 66; printed 64; patmi: AR2026 PDF 66; printed 64; operating_cash_flow: AR2026 PDF 71; printed 69; net_cash: derived [cash_and_equivalents|FY2025] - [borrowings|FY2025]; AR2026 PDF 68; printed 66.

FY2026: revenue: AR2026 PDF 66; printed 64; gross_profit: AR2026 PDF 66; printed 64; gross_margin: derived [gross_profit|FY2026] / [revenue|FY2026] * 100; AR2026 PDF 66; printed 64; profit_before_tax: AR2026 PDF 66; printed 64; patmi: AR2026 PDF 66; printed 64; operating_cash_flow: AR2026 PDF 71; printed 69; net_cash: derived [cash_and_equivalents|FY2026] - [borrowings|FY2026]; AR2026 PDF 68; printed 66.

Table sources and arithmetic

1HFY2024: revenue: OFFER PDF 243; printed B-4; gross_profit: OFFER PDF 243; printed B-4; gross_margin: derived [gross_profit|1HFY2024] / [revenue|1HFY2024] * 100; OFFER PDF 243; printed B-4; profit_before_tax: OFFER PDF 243; printed B-4; patmi: OFFER PDF 243; printed B-4; operating_cash_flow: OFFER PDF 246; printed B-7.

2HFY2024: revenue: derived [revenue|FY2024] - [revenue|1HFY2024]; AR2025 PDF 68; printed 66; OFFER PDF 243; printed B-4; gross_profit: derived [gross_profit|FY2024] - [gross_profit|1HFY2024]; AR2025 PDF 68; printed 66; OFFER PDF 243; printed B-4; gross_margin: derived [gross_profit|2HFY2024] / [revenue|2HFY2024] * 100; AR2025 PDF 68; printed 66; OFFER PDF 243; printed B-4; profit_before_tax: derived [profit_before_tax|FY2024] - [profit_before_tax|1HFY2024]; AR2025 PDF 68; printed 66; OFFER PDF 243; printed B-4; patmi: derived [patmi|FY2024] - [patmi|1HFY2024]; AR2025 PDF 68; printed 66; OFFER PDF 243; printed B-4; operating_cash_flow: derived [operating_cash_flow|FY2024] - [operating_cash_flow|1HFY2024]; AR2025 PDF 73; printed 71; OFFER PDF 246; printed B-7.

1HFY2025: revenue: HY2026 PDF 3; printed 3; gross_profit: HY2026 PDF 3; printed 3; gross_margin: derived [gross_profit|1HFY2025] / [revenue|1HFY2025] * 100; HY2026 PDF 3; printed 3; profit_before_tax: HY2026 PDF 3; printed 3; patmi: HY2026 PDF 3; printed 3; operating_cash_flow: HY2026 PDF 7; printed 7; net_cash: derived [cash_and_equivalents|1HFY2025] - [borrowings|1HFY2025]; HY2026 PDF 7; printed 7; OFFER PDF 244; printed B-5.

2HFY2025: revenue: derived [revenue|FY2025] - [revenue|1HFY2025]; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; gross_profit: derived [gross_profit|FY2025] - [gross_profit|1HFY2025]; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; gross_margin: derived [gross_profit|2HFY2025] / [revenue|2HFY2025] * 100; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; profit_before_tax: derived [profit_before_tax|FY2025] - [profit_before_tax|1HFY2025]; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; patmi: derived [patmi|FY2025] - [patmi|1HFY2025]; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; operating_cash_flow: derived [operating_cash_flow|FY2025] - [operating_cash_flow|1HFY2025]; AR2026 PDF 71; printed 69; HY2026 PDF 7; printed 7; net_cash: derived [cash_and_equivalents|2HFY2025] - [borrowings|2HFY2025]; AR2026 PDF 68; printed 66.

1HFY2026: revenue: HY2026 PDF 3; printed 3; gross_profit: HY2026 PDF 3; printed 3; gross_margin: derived [gross_profit|1HFY2026] / [revenue|1HFY2026] * 100; HY2026 PDF 3; printed 3; profit_before_tax: HY2026 PDF 3; printed 3; patmi: HY2026 PDF 3; printed 3; operating_cash_flow: HY2026 PDF 7; printed 7; net_cash: derived [cash_and_equivalents|1HFY2026] - [borrowings|1HFY2026]; HY2026 PDF 4; printed 4.

2HFY2026: revenue: derived [revenue|FY2026] - [revenue|1HFY2026]; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; gross_profit: derived [gross_profit|FY2026] - [gross_profit|1HFY2026]; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; gross_margin: derived [gross_profit|2HFY2026] / [revenue|2HFY2026] * 100; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; profit_before_tax: derived [profit_before_tax|FY2026] - [profit_before_tax|1HFY2026]; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; patmi: derived [patmi|FY2026] - [patmi|1HFY2026]; AR2026 PDF 66; printed 64; HY2026 PDF 3; printed 3; operating_cash_flow: derived [operating_cash_flow|FY2026] - [operating_cash_flow|1HFY2026]; AR2026 PDF 71; printed 69; HY2026 PDF 7; printed 7; net_cash: derived [cash_and_equivalents|2HFY2026] - [borrowings|2HFY2026]; AR2026 PDF 68; printed 66.

Table sources and arithmetic

FY2022: unsatisfied_performance_obligations: derived [unsatisfied_performance_obligations: Non-related parties|FY2022] + [unsatisfied_performance_obligations: Related companies|FY2022]; OFFER PDF 218; printed A-26; unsatisfied_performance_obligations: Related companies: OFFER PDF 218; printed A-26.

FY2023: unsatisfied_performance_obligations: derived [unsatisfied_performance_obligations: Non-related parties|FY2023] + [unsatisfied_performance_obligations: Related companies|FY2023]; OFFER PDF 218; printed A-26; unsatisfied_performance_obligations: Related companies: OFFER PDF 218; printed A-26.

FY2024: unsatisfied_performance_obligations: derived [unsatisfied_performance_obligations: Non-related parties|FY2024] + [unsatisfied_performance_obligations: Related companies|FY2024]; AR2025 PDF 89; printed 87; unsatisfied_performance_obligations: Related companies: AR2025 PDF 89; printed 87.

FY2025: unsatisfied_performance_obligations: derived [unsatisfied_performance_obligations: Non-related parties|FY2025] + [unsatisfied_performance_obligations: Related companies|FY2025]; AR2026 PDF 86-87; printed 84-85; unsatisfied_performance_obligations: Related companies: AR2026 PDF 86-87; printed 84-85.

FY2026: unsatisfied_performance_obligations: derived [unsatisfied_performance_obligations: Non-related parties|FY2026] + [unsatisfied_performance_obligations: Related companies|FY2026]; AR2026 PDF 86-87; printed 84-85; unsatisfied_performance_obligations: Related companies: AR2026 PDF 86-87; printed 84-85.

Questions the filings do not answer

A nominated subcontractor applied for adjudication over claimed subcontract work on 31 July 2026. The 1 September 2026 determination found an amount payable. LCC disputes entitlement and was preparing a stay application and arbitration; management said much of the cost was already accrued and did not expect a material impact. The amount and outcome remain unspecified.

The recovered filings do not provide a service-line profit split, current named-customer revenue concentration, a current bonding-capacity schedule, a complete contract-estimate and warranty-cohort bridge, or the subcontractor adjudication’s cash exposure. A subsequent issuer disclosure is needed to resolve each.

FY2022–FY2024 use combined pre-listing business accounts; FY2025–FY2026 use the reorganised consolidated group. The latest dedicated interim revises some prior-half comparatives without a reconciliation. Second-half flows here consistently subtract that interim from audited annual totals, rather than adopting conflicting separately printed second halves. No first-half accounts for FY2023 were recovered.

Sources

OFFER
Offer document · 2025-07-09
AR2025
Annual report FY2025 · 2025-10-08
HY2026
Interim results FY2026 · 2026-02-12
AR2026
Annual report FY2026 · 2026-10-07
SH-QA
Responses to shareholder questions · 2026-10-16
SGX-QA
Response to SGX query on the annual report · 2026-10-20
AGM-RESULT
AGM results · 2026-10-22
SGX-DIV
Final dividend timetable · 2026-10-07
DIRECTOR-R
Replacement director-interest notice · 2026-11-10
ISSUER-TAPE
Issuer announcement archive · 2026-11-17

The share-receipt classification difference is SGD9.585m in the cash statement less SGD8.304m net IPO proceeds and SGD1.218m placement receipts in the equity note: SGD0.063m. June closing net cash also serves as the second-half closing balance. The December closing balance for the earliest half was not recovered.

Company financial and order-book figures come from LCC filings, with physical PDF pages identified in the detailed notes. Market prices come from saved Yahoo Finance data; the BCA watchlist uses the external BCA source. Company filings are current to 17 November 2026; market prices are dated 20 November 2026. Older public reports retain their historical dates.

Issuer announcements · Issuer publications · SGX issuer page · Download tables (CSV)

Reader questions & corrections

Ask about this company, challenge a source or suggest a factual correction. Only selected questions that SMID Research has reviewed and answered are published.

No reader questions have been published yet.

Submit a private question or correction

Submissions are private by default. Your email is encrypted and never published. Please do not send confidential or inside information, allegations about individuals, promotions, or requests for personalised investment advice.

Connecting the secure submission form…

Secure-form fallback. Email your question or correction. Include the company name and disclose any position or relationship. Do not send confidential or inside information.

Behind the lock: Private record 🔒. Historical analysis remains access-controlled.

Chart notes and sources
  1. Original SMID Research comic. AI-assisted, monochrome artwork depicts the reported operating steps of Lum Chang Creations; captions and dated mix figures state the economics using issuer disclosures available to 2026-11-17. The drawings are representative—not issuer artwork, an exact product or site design, a statement of scale, or a company forecast.
  2. Revenue by half, SGD million. Source: the annual and interim revenue rows in the financial table; second halves are derived as annual less interim.

Transcripts

Find available event transcripts in the transcript library.

Browse company transcripts

Private vault

Open private vault